Item No
|
Description
|
Unit Unit Rate
|

01.1 Erection and maintenance of site office and removal thesame after
completion of work in accordance with the conditions of contract.In addition to the office required for his own use, the Contractor shall provide and maintain furnished field office for the use of the Engineer and his staff. The field office is to have a concrete floor, adequate foundation, brick walls, false ceiling of hard board with seasoned Garjan wood frame and painted, and all windows are to be glazed and provided with steel grill. Outside and inside wall surface are to be painted on plaster acceptable to the Engineer. The field office shall be maintained in a secure and watertight condition by the Contractor until the completion of the contract and shall be provided with electricity, running water and sewerage. All doors shall be fitted with approved locks and windows shall be provided with screen/blinds. Before construction the Contractor shall submit plans and drawings showing proposed details and location for the field office, including foundations, access roads, shades, layout of electrical and water supply and hard standings thereto for the approval of the engineer. The Engineer may require revision of the plans prior to giving approval for construction. The Contractor shall also submit details proposed furniture, fittings and other items of equipment and plant to the engineer for approval. These items shall be of the standard quality suitable for site. The office, complete with furnishings, fittings, access roads and hard standings shall be ready for occupation by the Engineer within 28 days of the date when the Contractor first occupies the site. The Contractor will provide day and night guards and a tea boy for the field office. At the end of the project all materials, equipment and plant, furniture, fittings recovered from dismantling the office and removing access road will be the property of the Contractor. No interim payment shall be certified unless Engineer’s office with required facilities are constructed and accepted by the Engineer.
(This is a time related item. Proportionate payment for this item shall be made distributing in each bill on the basis of percentage progress of the whole works under contract)

01.1.1
|
Engineer’s site office of minimum 15 sqm plinth area with providing
|
L.S.
|
125251.00
|
furniture, first aid-box, safety helmet, level / theodolite, consumables,
| |||
stationeries etc.
| |||
01.1.2
|
Engineer’s site office of minimum 38 sqm plinth area with providing security
|
L.S.
|
389014.00
|
fencing, 5 Kva stand-bye generator, furniture, first aid-box, safety helmet,
| |||
level / theodolite, consumables, stationeries etc.
| |||
1/166
Description
|
Unit
|
Unit Rate
| |
01.1.3
|
Engineer’s site office of minimum 38 sqm plinth area with providing security
|
L.S.
|
502145.00
|
fencing, 5 Kva stand-bye generator, IBM compatible PC with monitor,
| |||
uninterruptible power supply (UPS), Laserjet printer (minimum 25 ppm),
| |||
furniture, first aid-box, safety helmet, level/theodolite/EDM, consumables,
| |||
stationeries etc.
| |||
01.1.4
|
Engineer’s site office of minimum 38 sqm plinth area with providing security
|
L.S.
|
534467.00
|
fencing, 5 Kva stand-bye generator, IBM compatible PC with monitor,
| |||
uninterruptible power supply (UPS), Laserjet printer (minimum 25 ppm),
| |||
photocopier, 6 cft. Freeze, furniture, first aid-box, safety helmet,
| |||
level/theodolite/EDM, consumables, stationeries etc.
| |||
01.1.5
|
Engineer’s site office of minimum 10 sqm plinth area with providing
|
L.S.
|
23916.00
|
furniture, first aid-box, safety helmet, consumables, stationeries etc for low
| |||
value simple work of short duration (not more than six months).
| |||
01.1.6
|
Providing and maintenance window type 1800 BTU AC (Air-Cooler) for
|
each
|
52871.00
|
Engineer’s office and remove after completion of contract.
| |||
01.1.7
|
Providing and maintenance one project profile signboards of the size not
|
sqm.
|
207.00
|
exceeding 1 m x 2 m, to be placed at a suitable place of the site including
| |||
submission of proposals for the materials of the signboards and text layout
| |||
to the Engineer for approval which will be positioned as directed by the
| |||
Engineer and removing the same on completion of the Works or as
| |||
instructed by the Engineer.
| |||
01.2.1
|
Providing 3 sets as-built Drawings subject to Engineer’s approval
|
Per
|
19451.00
|
produced in AutoCAD software in 23.38” x 16.54” (A-2 size) standard
|
tender
| ||
drawing paper, and operating and maintenance manual of the equipment
| |||
and plant incorporated in the works, if any, in original by the date stated in
| |||
the Particular Conditions of Contract (PCC). If the Contractor does not
| |||
supply the as-built drawings and operating and maintenance manuals by
| |||
the date stated in the Particular Conditions of Contract (PCC), or they do
| |||
not receive the Engineer’s approval, the Engineer shall withhold the amount
| |||
stated in the PCC from the payments due to the Contractor.
| |||
The as-built drawings must show the permanent works as actually
| |||
constructed and reflect the revision of Tender Drawings and Drawings
| |||
supplied to the Contractor during the Contract as well as revisions of
| |||
drawings supplied by the Contractor during the Contract.
| |||
(One set of as-built drawings shall be considered for measurement and
| |||
payment)
| |||
01.2.2
|
Providing additional copy of as-built drawing produced in AutoCAD
|
sqm of
|
267.00
|
software in 23.38" x 16.54" (A-2) standard drawing paper accepted by the
|
drawing
| ||
Engineer.
|
sheet
| ||
e
| |||
01.2.3
|
Providing minimum ten (10) copies coloured post-card size progress
|
month
|
42.00
|
photograph of ‘works under contract’ taken by professional photographer
| |||
which record the progress of the Works.
| |||
01.2.4
|
Preparation & submission of implementation schedule to the Engineer for
|
Per
|
29165.00
|
approval prior ground breaking showing the events (works) and successive
|
tender
| ||
sub-events of works including all the management & control parameters
| |||
like Earliest Start Time (EST), Earliest Finish Time (EFT), float events on
| |||
critical path, resource allocation etc. with description of general method of
| |||
works, in orderly manner all in the form network diagram prepared in
| |||
computer software like MS project and presenting in Displayable hard and
| |||
soft copy minimum 3 (three) sets.
| |||
(This is a time related item. Proportionate payment for this item shall be
| |||
made distributing in each bill on the basis of percentage progress of the
| |||
whole works under contract)
| |||
01.2.5
|
Updating the Implementation Schedule and submission to the Engineer
|
month
|
12371.00
|
at intervals no longer than 28 days showing actual physical and financial
| |||
progress achieved, on each activity and the effect of the progress on the
| |||
timing of the remaining work, including any changes to the sequence of the
| |||
activities.
| |||
However, Engineer’s approval of the Programme shall not alter the
| |||
Contractor’s obligations. The Contractor may revise the Programme and
| |||
submit it to the Engineer again at any time. A revised programme shall
| |||
show the Variations and Events related to change of contract price.Month
| |||
wise documentation shall be the basis of payments on this item
| |||
01.2.6
|
Providing all necessary logistic support to frame ‘monthly progress
|
month
|
1802.00
|
meeting’ between Contractor/Contractor’s representatives and Employer /
| |||
Employer’s representatives at the Engineer's office at site.Month wise
| |||
documentation shall be the basis of payments on this item
| |||
01.3
|
Providing layout and carry over PWD Bench-Mark (BM) at site from
|
sqm.
|
4.00
|
nearby BM pillar, Property lines, existing ground level (EGL), formation
| |||
ground level (FGL), highest flood levels (HFL), plinth levels (PL), mean sea
| |||
level (MSL), setting and marking all pillars, marker, pegs etc. showing and
|
maintaining reduced levels (RL’s) including locating, establishing, protecting all public utilities within the premise of work and finally all to be presented in black and white.

01.4
|
Mobilization and cleaning site before commencing actual physical work
|
sqm.
|
21.00
|
and during contract period and demobilization after completion of the
| |||
Works under contract accepted by Engineer.
| |||
This work shall also covers clayey cleaning and clearing, cutting or filling,
| |||
dressing the project area on and in the ground to an extent that all the
| |||
events of works of the project can be executed smoothly in a working
| |||
environment with a particular attention on safety and security in all
| |||
respects, and to stockpile the end outcome to a place for disposal agreed
| |||
by the Engineer, where, payments are to be based on ground area
| |||
determined by the Engineer and be proportionate to the percentage
| |||
progress of work under contract as a whole in all respects and approved by
| |||
the Engineer.
| |||
1.5
|
Providing Expertised architect having relevant experience (s) more than
|
Per
|
60000.00
|
5years for detail documentation of architectural themes, drawings,
|
month
| ||
workingout shop drawings, communication with theme architect & getting
| |||
approval , specifying architectural needs according to approved master
| |||
architectural themes & plan, certifying as built drawing for the approval etc
| |||
& jobs assigned by the HOPE or his official at site (max man month not
| |||
greater than 1/4th of Project duration & payment for the item subject to
| |||
submission of CV & approved by approving authority)
| |||
1.6
|
Providing Expertised Engneer having relevant experience(s) more than
|
Per
|
100000.00
|
10years, for the project documentation, progress study & adjustment,
|
month
| ||
preparation of project Material schedule and Testing schdule for approval
| |||
etc. & jobs assigned by the HOPE or his official, at site (max man month
| |||
not greater than 1/4th of Project duration & payment for the item subject to
| |||
submission of CV & approved by approving authority)
| |||
1.7
|
Pick - up (double Cab) for transport of Test samples, work samples &
|
Per
|
65000.00
|
emmergency services etc. in/c fuel etc. (total usage not more than 1/6th of
|
month
| ||
project duration.)
|